This weeks progress on Americas Finest bow. It’s filling in at a steady pace…it is quite a dramatic site. This guy is right at the pinnacle, lets go inside. Then take a look out her bow. Lets back up further into… Continue Reading →

Week ~ 71 (Click on post image to view more images)

Americas Finest this week…If inclined see the difference from last week (#70) to see the progress on her bow. Hard to dispute her name. The next two images are different views of her today. Back in the Big House (fabrication… Continue Reading →

Week ~ 70 (Click on post image to view more images)

Now here’s a busy site. Because of the scale you have to look close to find the guy in the circle. By the way, inside that large circle is where the propeller will be installed. You get a first look… Continue Reading →

Week ~ 69 (Click on post image to view more images)

The post image from last weeks blog showed this smoke stack (exhaust pipe) being fabricated in the fab shop. Here it is being hauled up to Americas Finest to its intended location at the end of the engine compartment. Pipe… Continue Reading →