Floating Steel

Follow the construction of a Bering Sea Fishing Trawler from start to finsh

Tag

ship builders

First print exhibition of the floatingSteel Project – and the new “floatingSteel” book. (click on book cover for more info)

      First public showing will be at Northwind Arts Center 701 Water Street Port Townsend, WA.  

Week ~ 91 (Click on post image to view more images)

Installation of the forward gantry is in progress. And now a view from the West side. This is a huge gantry (crane) that has to be moved with great precision and coordination from a skilled crew at Dakota Creek. A… Continue Reading →

Week ~ 90 (Click on post image to view more images)

My first look at the power plant…it has been under wraps. And what these are I am not sure and would not venture a guess. I would not want to maintain them.   Now here is a hatch cover! Fishermans Finest,… Continue Reading →

Week ~ 85 (Click on post image to view more images)

A milestone in Americas Finest construction, her hull is all together. She’s almost full grown and what a magnificent sight! This last major module for her hull was just attached to her stern. You got a peak of this module… Continue Reading →

Week ~ 84 (Click on post image to view more images)

Four day weekend! Equipment gets well deserved rest. Lets look around. Looking towards the bow. On the main deck facing north towards huge spools that will work the nets. Now looking north towards the bow is the main cargo hold. Looks… Continue Reading →

Week ~ 83 (Click on post image to view more images)

The Big Move! This image encapsulates this monumental event for me as Americas Finest moves laterally (West) to get into a northern launch position as she points towards Alaska, her destiny. Before the move they are tearing down the old braces and discussing the… Continue Reading →

Week ~ 82 (Click on post image to view more images) all information given in these posts are from a non technical point of view…

How to move 2900 tons of steel on land, stay tuned! Here she is, Americas Finest, view Weeks 82 and next week (83). See her get prepared to be moved laterally (sidetracking) to a new position that will be her final orientation before her launch…. Continue Reading →

Week ~ 80 (Click on post image to view more images)

Americas Finest’s hull is in place as well as her name! This next image is the close up of her name. Her name is not painted on as you would expect. Each letter is cut out of steel and welded… Continue Reading →

Week ~ 78 (Click on post image to view more images)

Follow the images to watch the men plug up the last space on this deck. Check out the strange things brewing in the Big House (fab shop). Wow, what these guys can fabricate! Check back for an update. Our hull shot… Continue Reading →

Week ~ 77 (Click on post image to view more images) Happy New Year!

Busy at Dakota Creek Shipyards, all hands are working towards the launch of Americas Finest, and fine she is… Her propeller is set from last weeks installation. Another view of this majestic propeller. The first image is her bow nearing completion. The next two… Continue Reading →

© 2017 Floating Steel — Powered by WordPress

Theme by Anders NorenUp ↑